Kerala RERA has directed Sobha Limited and Puravankara Limited to pay ₹5 lakh in compensation to a homebuyer represented by Legacy Partners: ₹3 lakh for unauthorised use of his apartment and ₹2 lakh for mental agony, plus costs, with interest at 16.65% from the date he first raised the complaint.
Our client paid ₹2.88 crore for a four-bedroom apartment in a Kochi project, with possession promised by June 2022. When he visited in July 2024, the flat was being used as a site office. Possession finally came in October 2025.
Key takeaways for homebuyers
- Document everything the same day. Photographs taken during the inspection and emailed immediately became the decisive evidence.
- A handover certificate does not waive your rights. Signing it later does not wipe out the statutory right to compensation for what happened before possession.
- Frame claims carefully. RERA refused a separate rent claim as double recovery.
The matter was handled by Adv. Sherin Sheriyar, Adv. Shamjath Imran and Hashim Wafa. The order has been reported by Live Law.